Contracts will be awarded within 30 days. The projects are worth a combined $40 million.
Another 102 projects in greater Minnesota are in line for funding, and a list of projects in the Twin Cities area is coming later this month.
2009 Greater Minnesota ARRA Projects Let March 13, 2009:
1. Location: Hwy 10 – West of Motley
Description: Mill and overlay and road weather station installation
Construction start estimate: May 2009
Apparent low bid: $6,834,760.70
Contractor: Knife River Corporation
State Project # 7702-44
2. Location: Hwy 23 – Near New London
Description: Mill and overlay
Construction start estimate: September 2009
Apparent low bid: $1,123,474.16
Contractor: Knife River Corporation
State Project # 3408-13
3. Location: Hwy 75 – Ortonville to Graceville
Description: Mill and overlay
Construction start estimate: May 2009
Apparent low bid: $5,113,399.31
Contractor: Central Specialties Inc.
State Project # 0608-35
4. Location: I-90 – Hwy 74 to Hwy 43 in Winona County
Description: Bituminous overlay
Construction start estimate: May 2009
Apparent low bid: $4,484,583.93
Contractor: Dunn Blacktop Co.
State Project # 8580-154
5. Location: I-90 – CSAH 1 to Hwy 63 west of Stewartville
Description: Mill and overlay eastbound only
Construction start estimate: May 2009
Apparent low bid: $2,096,319.36
Contractor: Ulland Brothers Inc.
State Project # 5080-152
6. Location: I-90 Alden to Albert Lea
Description: Concrete overlay eastbound and bituminous overlay westbound
Construction start estimate: May 2009
Apparent low bid: $15,997,537.76
Contractor: Ulland Brothers Inc.
State Project #2481-50
7. Location: Hwy 93 – LeSueur
Description: Concrete replacement under railroad bridge and mill and overlay to Hwy 169
Construction start estimate: July 2009
Apparent low bid: $434,704.20
Contractor: Chard Tiling & Excavating Inc.
State Project #7213-11
8. Location: I-94 – East of Sauk Centre
Description: Install cable median guardrail
Construction start estimate: May 2009
Apparent low bid: $1,449,837.82
Contractor: H & R Construction Co.
State Project #7380-226
9. Location: Region-wide District 1
Description: Sign replacement
Construction start estimate: May 2009
Apparent low bid: $45,447.00
Contractor: Mo Diggin Inc.
State project #8821-186
10. Location: Region-wide District 6
Description: Guardrail replacement
Construction start estimate: May 2009
Apparent low bid: $1,685,285.76
Contractor: Mattison Contractors Inc.
State project #8826-68
11. Location: Region-wide District 7
Description: Install guardrail and end treatments
Construction start estimate: May 2009
Apparent low bid: $481,006.50
Contractor: Highway Technologies Inc.
State project #8827-88
TOTAL: $39,746,356.50
Greg Sitek